Troika Estates Private Limited
Deedo IDDD-PM86None of 2 registrations has reached its promised completion date yet.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Crosstown II C WingP51700055668 | Ulhasnagar (M Corp.) | Certificate Signed | 1 Feb 2029 | 1 Jun 2029 | +4 mo |
| Crosstown II A WingP51700056196 | Ulhasnagar | Certificate Signed | 1 Feb 2029 | 1 Jun 2029 | +4 mo |
Troika Estates Private Limited, in questions
Does Troika Estates Private Limited finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Troika Estates Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Troika Estates Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.