Trisha Developers
Deedo IDDD-2CEWOf 7 registrations whose promised date has arrived, 5 kept it (71%). The rest ran a median 32 mo late.
Delivery record
2 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SmrutiP52100006813 | Pune (M Corp.) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Shri Anand ShriP52100014402 | Pune (M Corp.) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| RajyogshreeP52100016035 | Kothrud | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| NirmalaP52100018072 | Erandwana | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Rahul ViharP52100025532 | Haveli | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Shradha ApartmentP52100025898 | Kothrud | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| PratibhaP52100029562 | Aundh | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | +35 mo* |
Trisha Developers, in questions
Does Trisha Developers finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 5 kept it (71%). The rest ran a median 32 mo late. Across Maharashtra, 73% kept their date.
How many projects has Trisha Developers registered with MahaRERA?
7 projects under 7 MahaRERA registrations; 5 completed on MahaRERA.
Does Trisha Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.