Company or firm · first RERA registration 2021
Trijal Enterprises
Deedo IDDD-S346Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 51 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay51 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Registration revoked | Trijal EnterprisesRegistration revoked / ab initio void: VINAYAK VATIKA BUILDERS AND DEVELOPERS · may refer to a related project | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Trijal EnterprisesP51700029550 | Adivali Dhokali | Certificate Signed | 1 Aug 2022 | 1 Aug 2022 | +51 mo* |
Trijal Enterprises, in questions
Does Trijal Enterprises finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 51 mo late. Across Maharashtra, 73% kept their date.
How many projects has Trijal Enterprises registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Trijal Enterprises have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology