Deedo IDDD-Y7VQOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 68 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| The Nest RealtyP52700013745 | Malkapur (Np) | Certificate Signed | 30 Mar 2021 | 30 Mar 2021 | +68 mo* |
The Nest Realty, in questions
Does The Nest Realty finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 68 mo late. Across Maharashtra, 73% kept their date.
How many projects has The Nest Realty registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does The Nest Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.