Tharwani Realtors
Deedo IDDD-2TWFOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 4 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tharwani Millennium CityP51700023782 | Badlapur | Certificate Signed | 30 Dec 2024 | 29 Jun 2025 | +23 mo* |
| Tharwani Millennium CityP51700023784 | Badlapur | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| Tharwani Millennium CityP51700023974 | Badlapur | Certificate Signed | 31 Jul 2023 | 31 Jul 2023 | On date |
| Tharwani PalladianP52000052621 | Kharghar | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
Tharwani Realtors, in questions
Does Tharwani Realtors finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Tharwani Realtors registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Tharwani Realtors have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.