Company or firm · first RERA registration 2017

Tata Value Homes Limited

Deedo IDDD-P9Q6

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 14 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay14 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
La MontanaP52100000145Wadagaon (Ct)Certificate Signed30 Sep 201930 Mar 2021+18 mo
La MontanaP52100033265Wadagaon (Ct)Certificate Signed31 Jan 202631 Jan 2026+10 mo*

Tata Value Homes Limited, in questions

Does Tata Value Homes Limited finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.

How many projects has Tata Value Homes Limited registered with MahaRERA?

1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Tata Value Homes Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology