Swati Sachin Khinvasara
Deedo IDDD-75ZBNone of 4 registrations has reached its promised completion date yet.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Swaraj City Amenity Bldg Phase 5P52100031162 | Ranjangaon Ganpati | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Swaraj CityP52100031171 | Saradwadi | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| Swaraj CityP52100031178 | Saradwadi | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Swaraj City Wing D Phase IVhaseP52100031252 | Saradwadi | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
Swati Sachin Khinvasara, in questions
Does Swati Sachin Khinvasara finish projects on time?
None of its 4 MahaRERA registrations has reached its promised completion date yet.
How many projects has Swati Sachin Khinvasara registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Swati Sachin Khinvasara have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.