Swaroop Construction

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date5 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree GaneshaP52100018755Talegaon Dabhade (M Cl)2018Certificate Signed30 Oct 202130 Oct 2021On date
Sunrise ResidencyP52100026592Talegaon Dabhade (M Cl)2020Certificate Signed30 Mar 202330 Mar 2023On date
Sunshine ResidencyP52100046364Talegaon Dabhade (M Cl)2022Certificate Signed31 Mar 202431 Mar 2024On date
Vallabh ResidencyP52100048628Talegaon Dabhade (M Cl)2023Certificate Signed31 Mar 202531 Mar 2025On date
Shreeja ResidencyP52100048971Talegaon Dabhade (M Cl)2023Certificate Signed24 Jun 202424 Jun 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree GaneshaOn date
  • Sunrise ResidencyOn date
  • Sunshine ResidencyOn date
  • Vallabh ResidencyOn date
  • Shreeja ResidencyOn date

Track record notes

  • 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology