Sushant Vijay Bhalbar
Deedo IDDD-Z1Z0Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 31 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Royal AnnexP53000017431 | Kagal (M Cl) | Certificate Signed | 1 Nov 2023 | 31 Dec 2025 | +25 mo |
| Royal OrchidP53000017548 | Kagal (M Cl) | Certificate Signed | 1 Nov 2023 | 1 Nov 2023 | +36 mo* |
Sushant Vijay Bhalbar, in questions
Does Sushant Vijay Bhalbar finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 31 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sushant Vijay Bhalbar registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sushant Vijay Bhalbar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.