Company or firm · first RERA registration 2022

Sushanku Realty Private Limited

Deedo IDDD-N2JT

None of 2 registrations has reached its promised completion date yet.

Projects12 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sushanku AvenueP51800046272AndheriCertificate Signed30 Nov 202630 Nov 2026On date
Sushanku AvenueP51800077600AndheriCertificate Signed31 Dec 202730 Apr 2028+4 mo

Sushanku Realty Private Limited, in questions

Does Sushanku Realty Private Limited finish projects on time?

None of its 2 MahaRERA registrations has reached its promised completion date yet.

How many projects has Sushanku Realty Private Limited registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Sushanku Realty Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology