Company or firm · first RERA registration 2018
Sun Realtors
Deedo IDDD-7ES2Of 1 registration whose promised date has arrived, 1 kept it (100%).
Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Centrum VillasQuarterly progress report not filed: CENTRUM VILLAS | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bafna Centrum Phase-1P99000018461 | Palghar | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Centrum VillasP99000050756 | Palghar | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
Sun Realtors, in questions
Does Sun Realtors finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Sun Realtors registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sun Realtors have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology