Sumer Builders
Deedo IDDD-Q951Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 28 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sumer Trinity Vertical Phase-IP51900017371 | Ward Gsouth | Certificate Signed | 30 Jun 2023 | 30 Jun 2024 | +40 mo* |
| Sumer AarambhP51900046330 | Ward Gsouth | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +16 mo* |
Sumer Builders, in questions
Does Sumer Builders finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 28 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sumer Builders registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Sumer Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.