Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 28 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay28 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sumer Trinity Vertical Phase-IP51900017371Ward GsouthCertificate Signed30 Jun 202330 Jun 2024+40 mo*
Sumer AarambhP51900046330Ward GsouthCertificate Signed30 Jun 202530 Jun 2025+16 mo*

Sumer Builders, in questions

Does Sumer Builders finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 28 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sumer Builders registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Sumer Builders have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.