Sumaira Enterprises

Deedo IDDD-G01Z

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 43 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay43 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Star Roshan City Building No-6 Wing IP99000021147DhansarCertificate Signed30 May 202331 Dec 2026+43 mo

Sumaira Enterprises, in questions

Does Sumaira Enterprises finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 43 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sumaira Enterprises registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Sumaira Enterprises have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology