Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Prithvi - H1P52100001317Kondhwa KhurdCertificate Signed22 Jul 201822 Jul 2018On date
Prithvi - H2P52100031366Kondhwa KhurdCertificate Signed30 Apr 202730 Apr 2027On date
Prithvi - H3PR1262022501312Kondhwa Khurd – ExtCertificate Signed25 Apr 203125 Aug 2031+4 mo

Sukumar Township Development Private Limited, in questions

Does Sukumar Township Development Private Limited finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Sukumar Township Development Private Limited registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Sukumar Township Development Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology