Skip to content
Individual promoter · first RERA registration 2021

Sugat Waghmare

Deedo IDDD-0S7Q

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 42 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay42 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rajgruh Magasvargiya Co-operative Housing Society Ltd. AkolaP50100031464Akola (M Corp.)Active30 Jun 202431 Dec 2027+42 mo

Sugat Waghmare, in questions

Does Sugat Waghmare finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sugat Waghmare registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Sugat Waghmare have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology