Suchitkumar Diwan Ramteke

Deedo IDDD-76D7

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 33 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay33 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Matrix Royal ResidencyP50500053229WanadongriCertificate Signed31 Mar 202631 Dec 2028+33 mo

Suchitkumar Diwan Ramteke, in questions

Does Suchitkumar Diwan Ramteke finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 33 mo late. Across Maharashtra, 73% kept their date.

How many projects has Suchitkumar Diwan Ramteke registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Suchitkumar Diwan Ramteke have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.