Space Associates
Deedo IDDD-ZK6EOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Park View 18P50500034312 | Khamla | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| Pebbles 21PR1190002601688 | Somalwada | Certificate Signed | 31 Mar 2029 | 31 Mar 2029 | On date |
Space Associates, in questions
Does Space Associates finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Space Associates registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Space Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.