Skip to content
Company or firm · first RERA registration 2022

Space Associates

Deedo IDDD-ZK6E

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay23 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Park View 18P50500034312KhamlaCertificate Signed31 Dec 202431 Dec 2024+23 mo*
Pebbles 21PR1190002601688SomalwadaCertificate Signed31 Mar 202931 Mar 2029On date

Space Associates, in questions

Does Space Associates finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.

How many projects has Space Associates registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Space Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology