Somani Landmarks LLP
Deedo IDDD-SXESNone of 2 registrations has reached its promised completion date yet.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Deshpande Somani SquarePM1260002600737 | Baramati (M Cl) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Gujar Somani ArcadePM1260002601313 | Jalochi | Certificate Signed | 1 Jul 2028 | 1 Nov 2028 | +4 mo |
Somani Landmarks LLP, in questions
Does Somani Landmarks LLP finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Somani Landmarks LLP registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Somani Landmarks LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.