Smw Builders And Developers
Deedo IDDD-YQEFOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai Anirudha DhamP52100028756 | Wadagaon (Ct) | Certificate Signed | 30 Jun 2024 | 30 Jun 2025 | +29 mo* |
| Riddhi Siddhi HeightsPR1260002501880 | Wadagaon (Ct) | Certificate Signed | 31 Jan 2029 | 31 May 2029 | +4 mo |
Smw Builders And Developers, in questions
Does Smw Builders And Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Smw Builders And Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Smw Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
