Skystar Buildcon Pvt. Ltd

Deedo IDDD-889Y

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 21 mo late — longer than Maharashtra's 4 mo.

Projects23 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay21 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sunteck City AvenueP51800001281BorivaliCertificate Signed30 Jun 202431 Dec 2026+30 mo
Sunteck City AvenueP51800002637BorivaliCertificate Signed30 Apr 202230 Apr 2023+12 mo
Sunteck PinnacleP51800028821BorivaliCertificate Signed30 Sep 202330 Sep 2023On date

Skystar Buildcon Pvt. Ltd, in questions

Does Skystar Buildcon Pvt. Ltd finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 21 mo late. Across Maharashtra, 73% kept their date.

How many projects has Skystar Buildcon Pvt. Ltd registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.

Does Skystar Buildcon Pvt. Ltd have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology