Skp Corp Private Limited
Deedo IDDD-GPFXOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aston PlazaP52100013383 | Ambegaon Bk | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| SKY PavilionP52100013569 | Undri | Certificate Signed | 30 Dec 2020 | 29 Jun 2022 | +18 mo |
| Aston PlazaP52100017499 | Ambegaon Bk | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| SKY PavilionP52100018243 | Undri | Certificate Signed | 30 Jun 2021 | 31 Dec 2026 | +66 mo |
Skp Corp Private Limited, in questions
Does Skp Corp Private Limited finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Skp Corp Private Limited registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Skp Corp Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.