Siraj Karim Pathan
Deedo IDDD-Q0JZOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Merc ApartmentP52800029383 | Ratnagiri (M Cl) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Haji Umar ComplexP52800080997 | Nachane (Ct) | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Siraj Karim Pathan, in questions
Does Siraj Karim Pathan finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Siraj Karim Pathan registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Siraj Karim Pathan have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.