Silver Satyam
Deedo IDDD-5D0NOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 47 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Silver SatyamP52100000036 | Pimpri Chinchawad (M Corp.) | Completed | 15 Oct 2020 | — | On date |
| Silver CentralP52100016761 | Chikhali | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +47 mo* |
Silver Satyam, in questions
Does Silver Satyam finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Silver Satyam registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Silver Satyam have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
