Sigma One Dhoot Ventures Previously Sigmaone Remonesa Ventures
Deedo IDDD-DDZ1Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Courtyard OneP52100004083 | Wakad | Certificate Signed | 30 Jun 2021 | 30 Jun 2021 | On date |
| Courtyard OneP52100005050 | Wakad | Certificate Signed | 31 May 2019 | 30 Nov 2020 | +18 mo |
Sigma One Dhoot Ventures Previously Sigmaone Remonesa Ventures, in questions
Does Sigma One Dhoot Ventures Previously Sigmaone Remonesa Ventures finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sigma One Dhoot Ventures Previously Sigmaone Remonesa Ventures registered with MahaRERA?
1 project under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Sigma One Dhoot Ventures Previously Sigmaone Remonesa Ventures have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.