Company or firm · first RERA registration 2017

Siddhivinayak Enterprises

Deedo IDDD-FFZE

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 26 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay26 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Riddhi Siddhi ApartmentP52000014482NeralCertificate Signed30 Dec 202230 Dec 2025+47 mo*
Krishna GloryP51700048182DombivliCertificate Signed31 Dec 202730 Apr 2028+4 mo

Siddhivinayak Enterprises, in questions

Does Siddhivinayak Enterprises finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 26 mo late. Across Maharashtra, 73% kept their date.

How many projects has Siddhivinayak Enterprises registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Siddhivinayak Enterprises have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology