Skip to content
Company or firm · first RERA registration 2018

Siddhivinayak Associates

Deedo IDDD-7NR4

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 3 registrations with dates has moved or missed its RERA date

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Siddheshwar ResidencyP52000016759Taloje MajkurCertificate Signed30 Dec 202230 Dec 2022On date
Siddheshwar Residency 2P52000023608Taloje MajkurCertificate Signed30 Dec 202430 Dec 2024On date
Orchid EnclaveP52000024194Taloje MajkurCertificate Signed30 Dec 202630 Dec 2026On date

Siddhivinayak Associates, in questions

Does Siddhivinayak Associates finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Siddhivinayak Associates registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Siddhivinayak Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology