Siddharth Real Ventures Limited Liability Partnership
Deedo IDDD-NTEWOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Saarrthi SerenityP52100001810 | Kothrud | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Saarrthi ShivalikP52100014200 | Kothrud | Certificate Signed | 30 Sep 2020 | 31 Mar 2021 | +6 mo |
Siddharth Real Ventures Limited Liability Partnership, in questions
Does Siddharth Real Ventures Limited Liability Partnership finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.
How many projects has Siddharth Real Ventures Limited Liability Partnership registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Siddharth Real Ventures Limited Liability Partnership have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.