Individual promoter · first RERA registration 2021

Shwetali Jitendra Sonigara

Deedo IDDD-MK72

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 32 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay32 mowhen late
First sales on record510registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Blue Dice Phase IIIP52100031264ChikhaliCertificate Signed31 Mar 202431 Mar 2026+32 mo*

Shwetali Jitendra Sonigara, in questions

Does Shwetali Jitendra Sonigara finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 32 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shwetali Jitendra Sonigara registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Shwetali Jitendra Sonigara have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology