Company or firm · first RERA registration 2021
Shubhankar Buildsol Llp
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| ChintamaniP52100030854 | Haveli | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Shubhankar PrarambhP52800050920 | Nachane (Ct) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology