Chintamani
Certificate SignedHaveli, Maharashtra 411052 |Promoter: Shubhankar Buildsol LLP
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 2BHK9 units in all
- Address
- CTS no 1206 Plot No 53 at Hingane Budruk Maharashi Karve Nagar, ANNASAHED CHIRMULE PATH, KARVE NAGARPIN 411052
- Designated bank account
- 212
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Sep 2024
The latest completion date on record passed 2 years and 1 month ago.
- Registered
- 20 Sep 2021
- Promised
- 30 Sep 2024
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100030854 | 20 Sep 2021 | 30 Sep 2024 | 30 Sep 2024 | Shubhankar Buildsol LLP | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Chintamani | 7 | 9 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 9 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 72.75 sq m · 783 sq ft | 5 | 0 |
| 2BHK | 73.33 sq m · 789 sq ft | 4 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 33 filings listed on MahaRERA's project page
Finance
- PAN CardShubhankar PAN.pdf · uploaded 13 Sep 2021Source
Legal
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Sep 2021Source
- 1 Declaration about Commencement CertificateDeclaration about commencement certificate.pdf · uploaded 8 Sep 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate.pdf · uploaded 8 Sep 2021Source
- 1 PAN CardShubhankar PAN.pdf · uploaded 13 Sep 2021Source
Show all 34 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportLegal Title report.pdf · uploaded 13 Sep 2021Source
- 1 Details of encumbrancesDeclaration for encumbrances.pdf · uploaded 13 Sep 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentSanction Plan (1).pdf · uploaded 13 Sep 2021Source
- 1 Declaration in FORM BForm B.pdf · uploaded 13 Sep 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate Final.pdf · uploaded 13 Sep 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Assurance certificate.pdf · uploaded 13 Sep 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 13 Sep 2021Source
- 1 Proforma of Allotment letterDeclaration for Draft Agreement.pdf · uploaded 13 Sep 2021Source
- 1 Copy of Layout Approval (in case of layout)Sanction Plan (1).pdf · uploaded 14 Sep 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 9 Jun 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate 81021.pdf · uploaded 9 Jun 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate 16032022.pdf · uploaded 9 Jun 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 RERA Dec21.pdf · uploaded 9 Jun 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sept 2021 CA Certificate.pdf · uploaded 9 Jun 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised plan 20 Dec23_11zon.pdf · uploaded 7 Mar 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate31122023 CN.pdf · uploaded 7 Mar 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 301223 CN.pdf · uploaded 7 Mar 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate CN 300923.pdf · uploaded 7 Mar 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate 300623 pdf.pdf · uploaded 7 Mar 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate -300623.pdf · uploaded 7 Mar 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Chintamani 31122023_11zon.pdf · uploaded 7 Mar 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Chintamani 30092023_11zon.pdf · uploaded 7 Mar 2024Source
Technical
Technical (Architect)
- DocumentArchitect Certificate31122023 CN.pdf · uploaded 7 Mar 2024Source
Technical (Engineer)
- DocumentEngineers Certificate 300623 pdf.pdf · uploaded 7 Mar 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
Survey, CTS, gat or plot numbers
Boundaries
- North
- Access Road
- South
- Plot No 60
- East
- Access Road
- West
- Plot No 54
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Prasad Bhatawadekar | — |
| Chartered accountant | Purushottam Pendse | — |
| Engineer | Vidyadhar Puranik | — |
| Other | Arun Gokahe | — |
| Other | Sachin Pampatwar | — |
Source: MahaRERA project page. Contact details are not shown.