Skip to content
Company or firm · first RERA registration 2025

Shrusti Nx

Deedo IDDD-QR31

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dhanalaxmi Chambers Premises Co Op Soc. LtdPC1330002500427Thane (M Corp.)Certificate Signed20 Dec 202720 Apr 2028+4 mo

Shrusti Nx, in questions

Does Shrusti Nx finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Shrusti Nx registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Shrusti Nx have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology