Company or firm · first RERA registration 2018

Shrivas Realties

Deedo IDDD-XHB1

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 91 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay91 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shrivas Tower VP50500015893NariCertificate Signed30 Apr 201929 Oct 2020+91 mo*

Shrivas Realties, in questions

Does Shrivas Realties finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 91 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shrivas Realties registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Shrivas Realties have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.