Shriram Developers
Deedo IDDD-YDSJOf 2 registrations whose promised date has arrived, 2 kept it (100%).
Delivery record
None of 2 registrations with dates has moved or missed its RERA date
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shriram ShrustiP52700016263 | Godoli (Ct) | Certificate Signed | 30 Apr 2022 | 30 Apr 2022 | On date |
| Vinayak SrushtiP52700021958 | Satara | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
Shriram Developers, in questions
Does Shriram Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Shriram Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Shriram Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.