Skip to content
Company or firm · first RERA registration 2019

Shripatii Realtors Pvt Ltd

Deedo IDDD-2TN3

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 38 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay38 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Jashraj ClassicP51700022346Navi Mumbai (M Corp.)Certificate Signed30 Sep 202331 Dec 2024+38 mo*

Shripatii Realtors Pvt Ltd, in questions

Does Shripatii Realtors Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 38 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shripatii Realtors Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Shripatii Realtors Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology