Shri Swami Samarth Estates
Deedo IDDD-R1ZBNone of 2 registrations has reached its promised completion date yet.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shri Swami Samarth HeightsP51100050651 | Wadi Bk. | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Shri Swami Samarth Heights-KauthaPR1200002502744 | Koutha | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
Shri Swami Samarth Estates, in questions
Does Shri Swami Samarth Estates finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Shri Swami Samarth Estates registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Shri Swami Samarth Estates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.