Shri Narayana Builders
Deedo IDDD-DEDCOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 20 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Narayana ResidencyP51500022026 | Hirapur | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| Shri Niwasa ResidencyP51500053325 | Hirapur | Certificate Signed | 31 Mar 2025 | 31 Dec 2025 | +20 mo* |
Shri Narayana Builders, in questions
Does Shri Narayana Builders finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shri Narayana Builders registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Shri Narayana Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.