Shri Krishna Chaitanya Enterprises
Deedo IDDD-KBN6Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Jeevan Kanchan Co-Operative Housing Society Ltd.P51800000014 | Andheri | Certificate Signed | 30 Mar 2018 | 30 Mar 2018 | On date |
| Radha KrishnaP51800012626 | Borivali | Certificate Signed | 30 Sep 2018 | 30 Sep 2019 | +12 mo |
| Radha Madhav CHSLP51800005539 | Borivali | Certificate Signed | 30 Sep 2018 | 30 Sep 2019 | +12 mo |
Shri Krishna Chaitanya Enterprises, in questions
Does Shri Krishna Chaitanya Enterprises finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shri Krishna Chaitanya Enterprises registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Shri Krishna Chaitanya Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.