Shrey Infra Project

Deedo IDDD-43DZ

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay8 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Misri Villa HeightP52000003140BokadviraCertificate Signed31 May 201831 Aug 2018+3 mo
Sky CopperP52000017618BokadviraCertificate Signed15 Aug 202314 Aug 2024+12 mo

Shrey Infra Project, in questions

Does Shrey Infra Project finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shrey Infra Project registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Shrey Infra Project have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology