Company or firm · first RERA registration 2017
Shreenath Developers
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).
Projects22 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Royal CastleP51700010834 | Ambarnath(M Cl) | Certificate Signed | 30 Nov 2020 | 31 Mar 2024 | +40 mo |
| Royal Castle Phase 2P51700021992 | Ambarnath (R) | Not on record | 30 Dec 2023 | 31 Jan 2027 | +37 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology