Skip to content

Royal Castle Phase 2

Certificate Signed

Ambarnath (R), Thane 421501 |Promoter: Shreenath Developers

Residential / Group HousingRERAP51700021992
25 Aug 2019Registered with MahaRERA
30 Dec 2023Promised completion
31 Jan 2027Revised completionPushed back 3 years and 1 month
1Building
106Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 1RK, Shop106 units in all
Address
S No 83 H No 1 Plot No 2, Village Pale, AmbernathPIN 421501
Designated bank account
82
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.18000, 73.18000
Royal Castle Phase 2 is at latitude 19.18000, longitude 73.18000.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years and 1 month

Registered
25 Aug 2019
Promised
30 Dec 2023
Revised
31 Jan 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002199225 Aug 201930 Dec 202331 Jan 2027Shreenath DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Maiden Castle7106

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 106 units booked (0%), as the promoter reported to MahaRERA

1BHK · 84 units1RK · 7 unitsShop · 15 units
TypeCarpet areaUnitsBooked
1BHK29.7 sq m · 320 sq ft140
1BHK30.29 sq m · 326 sq ft70
1BHK31.08 sq m · 335 sq ft70
1BHK31.65 sq m · 341 sq ft70
1BHK31.79 sq m · 342 sq ft70
1BHK32.59 sq m · 351 sq ft70
1BHK32.79 sq m · 353 sq ft70
1BHK33.74 sq m · 363 sq ft70
Show all 19 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK34.15 sq m · 368 sq ft70
1BHK34.22 sq m · 368 sq ft140
1RK22.57 sq m · 243 sq ft70
Shop10.26 sq m · 110 sq ft20
Shop10.44 sq m · 112 sq ft10
Shop11.57 sq m · 125 sq ft20
Shop12.23 sq m · 132 sq ft10
Shop12.24 sq m · 132 sq ft10
Shop12.48 sq m · 134 sq ft10
Shop13.2 sq m · 142 sq ft60
Shop14.16 sq m · 152 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 129 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardShreenath developers pan.pdf · uploaded 2 Aug 2021Source

Legal

  • Legal Title reporttitle certificate.pdf · uploaded 6 Aug 2019Source
  • Declaration Form BForm B.pdf · uploaded 8 Aug 2019Source
  • Declaration Form Bform b.pdf · uploaded 14 Apr 2025Source
  • Declaration Form BForm B updated.pdf · uploaded 11 Jun 2025Source

Migrated

  • 1 Copy of the legal title reporttitle certificate.pdf · uploaded 6 Aug 2019Source
Show all 131 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancestitle certificate.pdf · uploaded 6 Aug 2019Source
  • 1 Copy of Layout Approval (in case of layout)Layout 2.pdf · uploaded 6 Aug 2019Source
  • 1 Building Plan Approval (IOD)Layout 1.pdf · uploaded 6 Aug 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 6 Aug 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 6 Aug 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FINAL FORM 2.pdf · uploaded 6 Aug 2019Source
  • 1 Certificates of CA (Form 3)FORM 3.pdf · uploaded 6 Aug 2019Source
  • 1 Proforma of Allotment letterAllotment and proforma.pdf · uploaded 6 Aug 2019Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 8 Aug 2019Source
  • 1 PAN CardShreenath developers pan.pdf · uploaded 2 Aug 2021Source
  • 1 Declaration about Commencement Certificatedeclaration.pdf · uploaded 26 Feb 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 83-1.pdf · uploaded 27 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 83-1.pdf · uploaded 27 Apr 2022Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY_compressed.pdf · uploaded 10 May 2022Source
  • 2 Disclosure of sold/ booked inventorydisclosure of sold unsold inventory_compressed (1).pdf · uploaded 5 Jul 2022Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Jul 2022Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Jul 2022Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Jul 2022Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Jul 2022Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Jul 2022Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Jul 2022Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Jul 2022Source
  • 2 Certificates of CA (Form 3)Form -3_.pdf · uploaded 19 Jul 2022Source
  • 3 Certificates of CA (Form 3)Form -3.pdf · uploaded 19 Jul 2022Source
  • 4 Certificates of CA (Form 3)Form -3.pdf · uploaded 19 Jul 2022Source
  • 5 Certificates of CA (Form 3)Form -3.pdf · uploaded 19 Jul 2022Source
  • 6 Certificates of CA (Form 3)Form -3.pdf · uploaded 19 Jul 2022Source
  • 7 Certificates of CA (Form 3)Form -3.pdf · uploaded 19 Jul 2022Source
  • 8 Certificates of CA (Form 3)Form -3.pdf · uploaded 19 Jul 2022Source
  • 9 Certificates of CA (Form 3)Form -3.pdf · uploaded 19 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Fom 5.pdf · uploaded 19 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.pdf · uploaded 19 Jul 2022Source
  • 1 Declaration in FORM Bform b.pdf · uploaded 14 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorydisclosure of sold and unsold.pdf · uploaded 14 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)fORM 2A 23.pdf · uploaded 23 Apr 2025Source
  • 1 Proforma of Agreement for saleModel AFS.pdf · uploaded 23 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 2024.pdf · uploaded 23 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2a 2025.pdf · uploaded 23 Apr 2025Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 23-24 Q1.pdf · uploaded 24 May 2025Source
  • 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 24-25 Q4.pdf · uploaded 24 May 2025Source
  • 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 24-25 Q3.pdf · uploaded 24 May 2025Source
  • 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 24-25 Q2.pdf · uploaded 24 May 2025Source
  • 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 24-25 Q1.pdf · uploaded 24 May 2025Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 23-24 Q4.pdf · uploaded 24 May 2025Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 23-24 Q3.pdf · uploaded 24 May 2025Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 23-24 Q2.pdf · uploaded 24 May 2025Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 23-24 Q1.pdf · uploaded 24 May 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 21-22 Q1.pdf · uploaded 24 May 2025Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 22-23 Q4.pdf · uploaded 24 May 2025Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 22-23 Q3.pdf · uploaded 24 May 2025Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 22-23 Q2.pdf · uploaded 24 May 2025Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 22-23 Q1.pdf · uploaded 24 May 2025Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 21-22 Q4.pdf · uploaded 24 May 2025Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 21-22 Q3.pdf · uploaded 24 May 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FY 21-22 Q2.pdf · uploaded 24 May 2025Source
  • 1 Certificates of CA (Form 3)FY 21-22 Q1.pdf · uploaded 30 May 2025Source
  • 2 Certificates of CA (Form 3)FY 21-22 Q2.pdf · uploaded 30 May 2025Source
  • 3 Certificates of CA (Form 3)FY 21-22 Q3.pdf · uploaded 30 May 2025Source
  • 4 Certificates of CA (Form 3)FY 21-22Q4.pdf · uploaded 30 May 2025Source
  • 5 Certificates of CA (Form 3)FY 22-23 Q1.pdf · uploaded 30 May 2025Source
  • 6 Certificates of CA (Form 3)FY 22-23 Q2.pdf · uploaded 30 May 2025Source
  • 7 Certificates of CA (Form 3)FY 22-23 Q3.pdf · uploaded 30 May 2025Source
  • 8 Certificates of CA (Form 3)FY 22-23 Q4.pdf · uploaded 30 May 2025Source
  • 9 Certificates of CA (Form 3)FY 23-24 Q1.pdf · uploaded 30 May 2025Source
  • 10 Certificates of CA (Form 3)FY 23-24 Q2.pdf · uploaded 30 May 2025Source
  • 11 Certificates of CA (Form 3)FY 23-24 Q3.pdf · uploaded 30 May 2025Source
  • 12 Certificates of CA (Form 3)FY 23-24 Q4.pdf · uploaded 30 May 2025Source
  • 13 Certificates of CA (Form 3)FY 24-25 Q1.pdf · uploaded 30 May 2025Source
  • 14 Certificates of CA (Form 3)FY 24-25 Q2.pdf · uploaded 30 May 2025Source
  • 15 Certificates of CA (Form 3)FY 24-25 Q3.pdf · uploaded 30 May 2025Source
  • 16 Certificates of CA (Form 3)FY 24-25 Q4.pdf · uploaded 30 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)2021-22.pdf · uploaded 9 Jun 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)2023-24.pdf · uploaded 9 Jun 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)2022-23.pdf · uploaded 9 Jun 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)2024-25.pdf · uploaded 9 Jun 2025Source
  • 1 Declaration in FORM BForm B updated.pdf · uploaded 11 Jun 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)March 22.pdf · uploaded 11 Jun 2025Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)June 22.pdf · uploaded 11 Jun 2025Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)SEP 22.pdf · uploaded 11 Jun 2025Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Dec 22.pdf · uploaded 11 Jun 2025Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)March 23.pdf · uploaded 11 Jun 2025Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)June 23.pdf · uploaded 11 Jun 2025Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)SEP 23.pdf · uploaded 11 Jun 2025Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Dec 23.pdf · uploaded 11 Jun 2025Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)March 24.pdf · uploaded 11 Jun 2025Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)June 24.pdf · uploaded 11 Jun 2025Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sep 24.pdf · uploaded 11 Jun 2025Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Dec 24.pdf · uploaded 11 Jun 2025Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)March 25.pdf · uploaded 11 Jun 2025Source

Technical

  • DocumentLayout 2.pdf · uploaded 6 Aug 2019Source
  • DocumentLayout 1.pdf · uploaded 6 Aug 2019Source

Technical (Architect)

  • DocumentFORM 1.pdf · uploaded 6 Aug 2019Source
  • DocumentMarch 22.pdf · uploaded 11 Jun 2025Source
  • DocumentJune 22.pdf · uploaded 11 Jun 2025Source
  • DocumentSEP 22.pdf · uploaded 11 Jun 2025Source
  • DocumentDec 22.pdf · uploaded 11 Jun 2025Source
  • DocumentMarch 23.pdf · uploaded 11 Jun 2025Source
  • DocumentJune 23.pdf · uploaded 11 Jun 2025Source
  • DocumentSEP 23.pdf · uploaded 11 Jun 2025Source
  • DocumentDec 23.pdf · uploaded 11 Jun 2025Source
  • DocumentMarch 24.pdf · uploaded 11 Jun 2025Source
  • DocumentJune 24.pdf · uploaded 11 Jun 2025Source
  • DocumentSep 24.pdf · uploaded 11 Jun 2025Source
  • DocumentDec 24.pdf · uploaded 11 Jun 2025Source
  • DocumentMarch 25.pdf · uploaded 11 Jun 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 19 Jul 2022Source
  • DocumentFY 21-22 Q1.pdf · uploaded 24 May 2025Source
  • DocumentFY 21-22 Q2.pdf · uploaded 24 May 2025Source
  • DocumentFY 21-22 Q3.pdf · uploaded 24 May 2025Source
  • DocumentFY 21-22 Q4.pdf · uploaded 24 May 2025Source
  • DocumentFY 22-23 Q1.pdf · uploaded 24 May 2025Source
  • DocumentFY 22-23 Q2.pdf · uploaded 24 May 2025Source
  • DocumentFY 22-23 Q3.pdf · uploaded 24 May 2025Source
  • DocumentFY 22-23 Q4.pdf · uploaded 24 May 2025Source
  • DocumentFY 23-24 Q1.pdf · uploaded 24 May 2025Source
  • DocumentFY 23-24 Q1.pdf · uploaded 24 May 2025Source
  • DocumentFY 23-24 Q2.pdf · uploaded 24 May 2025Source
  • DocumentFY 23-24 Q3.pdf · uploaded 24 May 2025Source
  • DocumentFY 23-24 Q4.pdf · uploaded 24 May 2025Source
  • DocumentFY 24-25 Q1.pdf · uploaded 24 May 2025Source
  • DocumentFY 24-25 Q2.pdf · uploaded 24 May 2025Source
  • DocumentFY 24-25 Q3.pdf · uploaded 24 May 2025Source
  • DocumentFY 24-25 Q4.pdf · uploaded 24 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ambarnath (R), Ambarnath taluka

Survey, CTS, gat or plot numbers

S NO 83 H NO 1 PLOT NO 2

Boundaries

North
S No 82 H No 4
South
S No 83 H No 2
East
Midc Compound
West
Fanshipada

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPramod Kamble—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology