Shreenath Constructions
Deedo IDDD-SB9FOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 3 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Building C - DP51500009104 | Aurangabad (M Corp.) | Completed | 31 May 2018 | — | On date |
| Shreenath Residency Building A-BP51500010298 | Aurangabad (M Corp.) | Certificate Signed | 31 Aug 2026 | 31 Aug 2026 | +3 mo* |
Shreenath Constructions, in questions
Does Shreenath Constructions finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 3 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shreenath Constructions registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Shreenath Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.