Company or firm · first RERA registration 2017

Shreenath Constructions

Deedo IDDD-SB9F

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 3 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay3 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Building C - DP51500009104Aurangabad (M Corp.)Completed31 May 2018—On date
Shreenath Residency Building A-BP51500010298Aurangabad (M Corp.)Certificate Signed31 Aug 202631 Aug 2026+3 mo*

Shreenath Constructions, in questions

Does Shreenath Constructions finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 3 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shreenath Constructions registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Shreenath Constructions have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology