Shree Venkatesh Buildcon
Deedo IDDD-Y7A2Of 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
None of 4 registrations with dates has moved or missed its RERA date
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Venkatesh SkydaleP52100021836 | Vitthalvadi | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Venkatesh Skydale Phase 2P52100024644 | Vitthalvadi | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Venkatesh SkydaleP52100025576 | Vitthalvadi | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Venkatesh SkydaleP52100025615 | Vitthalvadi | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
Shree Venkatesh Buildcon, in questions
Does Shree Venkatesh Buildcon finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Shree Venkatesh Buildcon registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Shree Venkatesh Buildcon have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.