Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 19 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay19 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vrundavan ParkP51700049309DevrungCertificate Signed31 Mar 202531 Dec 2027+33 mo
Vrundavan Park JaswandiPR1330002501246DevrungCertificate Signed30 Jun 202830 Oct 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology