Shree Swami Sanket Enterprises
Deedo IDDD-M9F7None of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Devyani CHSPM1330002500168 | Naupada | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 mo |
Shree Swami Sanket Enterprises, in questions
Does Shree Swami Sanket Enterprises finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Shree Swami Sanket Enterprises registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Shree Swami Sanket Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.