Shree Saishraddha Developers & Builders

Deedo IDDD-Y4P3

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vrundavan ParkP52100018019ShikrapurCertificate Signed17 Sep 202117 Mar 2023+18 mo

Shree Saishraddha Developers & Builders, in questions

Does Shree Saishraddha Developers & Builders finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shree Saishraddha Developers & Builders registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Shree Saishraddha Developers & Builders have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.