Deedo IDDD-AF4BOf 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Girdhari HeightsP99000029298 | Vasai Virar City (M Corp) | Certificate Signed | 30 Apr 2026 | 30 Apr 2026 | On date |
| Vandana ResidencyPR1240002501274 | Vasai Virar City (M Corp) | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 mo |
Shree Krishna Developers, in questions
Does Shree Krishna Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Shree Krishna Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Shree Krishna Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.