Shree Krishna Buildcon

Deedo IDDD-P0FW

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Aawas DeepP51700014893Badlapur (M Cl)Certificate Signed30 Dec 202230 Dec 2022On date
Shreeji SparshP52800077960Dapoli CampCertificate Signed31 Aug 203131 Dec 2031+4 mo