Shree Gajanan Builders And Developers
Deedo IDDD-5JN8Of 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
None of 5 registrations with dates has moved or missed its RERA date
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gajanan PalaceP50500002858 | Nagpur (M Corp.) | Certificate Signed | 30 Mar 2018 | 30 Mar 2018 | On date |
| Gajanan ResidencyP50500020557 | Nagpur (M Corp.) | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| Gajanan EnclaveP50500032517 | Nagpur (M Corp.) | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Gajanan HeightsP50500052627 | Nagpur (M Corp.) | Certificate Signed | 31 Aug 2025 | 31 Aug 2025 | On date |
| Gajanan MeadowsP50500080247 | Nagpur (M Corp.) | Active | 31 Mar 2028 | — | On date |
Shree Gajanan Builders And Developers, in questions
Does Shree Gajanan Builders And Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Shree Gajanan Builders And Developers registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 4 completed on MahaRERA.
Does Shree Gajanan Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.