Shree Bhagwati Construction
Deedo IDDD-58K9Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vitthal AnghanP52100017238 | Aalandi | Certificate Signed | 30 Jun 2021 | 30 Jun 2022 | +12 mo |
| Panache FloraP52100053069 | Ravet | Certificate Signed | 31 Oct 2026 | 28 Feb 2027 | +4 mo |
Shree Bhagwati Construction, in questions
Does Shree Bhagwati Construction finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Bhagwati Construction registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Shree Bhagwati Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.