Shree Balaji Builders And Developers
Deedo IDDD-B4Z0Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 108 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Venkatesh Kumkum Bldg No 10P51700003994 | Mirabhayandar (M Corp.) | Certificate Signed | 30 Dec 2023 | 31 Dec 2032 | +108 mo |
| Venkatesh Jyot Bldg No 5P51700006779 | Bhayandar | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
Shree Balaji Builders And Developers, in questions
Does Shree Balaji Builders And Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 108 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Balaji Builders And Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Shree Balaji Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.